2015-04-27T11:24:57+05:30
(b) 22.5 days is the answer.
0
2015-04-27T12:46:03+05:30
Work ratio ->A:B=3:1
hence time ratio,reverse of work ratio ->A:B=1:3
let x be day taken by B to complete work
hence x-60 days taken by A according to question
x-60/x=1/3
after solving this equation
answer will be x=90
and b=x-60=30
together they finishe work in  1/30+1/90

=2/45 = 22.5 days
0