Given,
X=2y
X+Y=18
2Y+Y=18
3Y=18
Y=6
=>X=2×6
=>X=12
therefore x will finish the work in 12 days Hope it helps u
0
2016-03-24T19:39:37+05:30
A=2:1
a+b in a day=1/18
b in a day=1/8 * 1/3
                =1/54
so b=54days