Duration along the critical path defines which of the following ?1. Shortest duration needed2. Shortest duration permissible3. Longest duration needed4. Longest duration permissibleSelect the correct answer using the code given below :

A. 1 and 2 only B. 1 and 4 only C. 2 and 3 only D. 3 and 4 only

1

Answers

2014-08-14T03:08:15+05:30

This Is a Certified Answer

×
Certified answers contain reliable, trustworthy information vouched for by a hand-picked team of experts. Brainly has millions of high quality answers, all of them carefully moderated by our most trusted community members, but certified answers are the finest of the finest.
2. Shortest duration permissible