Work done by A in 1 day = 1/10
Work done by B in 1 day = 1/15
Therefore, work done by them together in one day...
--> 1/10 + 1/15
--> 25/150
--> 1/6
And that means.. they will complete the work together in 6 days
0
if they work together for 5 days!
what do u mean by this
that means they'll finish 5/6th of the work in 5 days