We use generally the following formula for calculation of the expected completion time :
     1/6 * (Optimistic estimate + pessimistic estimate + 4 * most likely estimate)
 So we have : 1/6 (4+12 + 4* 11) = 60/6 = 10 days

1 5 1
2014-08-19T22:52:11+05:30

This Is a Certified Answer

×
Certified answers contain reliable, trustworthy information vouched for by a hand-picked team of experts. Brainly has millions of high quality answers, all of them carefully moderated by our most trusted community members, but certified answers are the finest of the finest.
The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion timeof this activity is C. 10 days
0