Anuj And Bhanu in 20 days have finished 20/30= 2/3 of work
The work left was 1-2/3=1/3

Anuj finished the work 1/3 work in 20 days

Anuj would finish the whole work in 1*20/(1/3)=60 days

Ans-60days
1 2 1
2014-12-16T19:48:44+05:30
Anuj can finish the work alone in 60 days