Answers

2015-01-04T14:28:48+05:30
Volume of the wall = 2400*500*25= 30000000 cm³
Volume of brick= 25*12.5*7.5=2343.75
Volume to be covered by sand & cement is 5%
          Hence volume covered by brick =(100-5)%=95%
Volume of wall to be covered by brick= 30000000*95/100= 28500000
 No. of brick required=28500000/2343.75= 12160
No. of brick used are 12160
0
please mark as the best...........
Sure !
But why did we minus (hundered-5)% ??
100 % wall is made of 5% cement and rest by bricks
Okay.